![]()
![]() |
![]() |
... |
| The renovation tear out begins (mid-July 2011). | Other cladding is being removed also. | ... |
- Temple renovations 2011 - The first
week. The tear out begins (mid-July 2011).
- The portico supporting columns are
exposed; and the underside of the portico roof is being readied.
- The flowers and shrubs on the North
grounds are as beautiful and peaceful as ever (late July).
- The tiered garden walls have been
completely dismantled along with the walkways (early August).
- Jacks hold up the portico roof
so it stays in place as the supporting columns are removed.
- The patio bricks and remnants of
the walkways and tiered garden walls are removed along with their encased
rebar (steel reinforcing bars).
- Footings are being poured in late
August for the East wall and foundation of the new entryway.
- The supporting columns are back in
place holding up the portico roof. Additional footings and uprights
have been poured.
- Forms for the foundation of the platform
are taking shape directly under the portico roof, and extending to
the East.
- In early September, Outer forms have
been removed from one poured footing (center, left).
- By mid-September, more of the platform
foundation elements are in place.
- Toward the end of September, the
portico enclosure framing takes shape.
- 29 Sept 2011 - The day of the BIG
POUR. The forms and rebar for the main slab of the platform are readied.
- The top tier of the North bulkhead
is finished. It will keep the
platform concrete at the top of the staircase.
- And unfolds like a giant praying
mantis to start the pour at the south end of the platform.
- Early in October, the portico enclosure
is nearly complete.
- By the Canadian Thanksgiving weekend, the
planter walls along the East platform wall have been poured.
- The planter wall North of the stairs
has also been poured (foreground, right).
- Two art glass
windows are in place, ... one to go before the re-opening on 29 Nov
2011.
- The temporary
entryway at the top of the North wheel chair ramp is marked on the
unfinished North portico wall exterior.
Return
to top of prior series, this
series, next series.
Return
to the Edmonton Temple page, its Table
of Contents or its Related Sources.
Return
to the
Meek
Family Home Page, or its Table
of Contents.